PERTH-based smartcard specialist ERG is not giving up without a fight, and may now launch a $250 million damages claim against the NSW state government over the Tcard public transport ticketing debacle.

 
Delayed NSW Tcard finally collapses

NEARLY ten years after embarking on a plan to build an integrated ticketing system for all public transport, the NSW Government has scrapped its controversial Tcard project after countless delays and cost overruns.

 
Privacy still a top online concern: Survey
ONE quarter of Australians say they regularly provide false information on online forms as a way of protecting their privacy, according to a national survey commissioned by the Office of the Australian Privacy Commissioner.
 
Ellison on card privacy – ‘We have the technology’

NEWLY-installed Human Services Minister Chris Ellison has moved quickly to soothe Access Cards opponents as government prepares for a second shot at getting the smartcard proposal through the Senate.

 
ERG loads $250m lawsuit canon PDF Print E-mail
Written by James Riley   
Wednesday, 30 January 2008

PERTH-based smartcard specialist ERG is not giving up without a fight, and may now launch a $250 million damages claim against the NSW state government over the Tcard public transport ticketing debacle.

Chairman Colin Henson said the company was considering legal action over what it describes as “the NSW Government’s unlawful termination of the Tcard contract.” ERG said it had so far identified losses associated with the termination to be approximately $250 million.

The company is now squaring off against the NSW Government, which itself has threatened to sue ERG to recover $95 million of taxpayer funding.

Mr Henson said in a statement that the government had been a difficult partner to work with, and that the project was characterised by a lack of leadership and disinterest by Transport Minister John Watkins and senior bureaucrats.

He said the ERG subsidiary handling the project – Integrated Ticketing Solutions Limited (ITSL) – had presented the Government’s Public Transport Ticketing Corporation (PTTC) with a plan last November that could have seen the Tcard system rolled out over the next 18 months.

“The program was backed by an independent, reputable Sydney based Project Management consultant specifically engaged to assess the program,” Mr Henson said.

“Despite the quality of the program, apart from superficial comment and questioning, the Government and the PTTC chose to ignore it. This is typical of the lack of communication and co-operation shown by the PTTC and the Government since the contract with ITSL/ERG was signed in 2003.”

“It needs to be remembered that ERG has successfully delivered similar programs with cooperative Government departments in cities all around the world (including San Francisco, Singapore, Hong Kong, and other cities much larger than Sydney), and many of ERG’s current project customers have provided references supporting the company,” he said.

 
About CeBIT Australia

CeBIT Australia is Australasia's leading Information & Communications Technology (ICT) event for the business marketplace and covers the entire spectrum of technology and the key elements that make up the ICT products and services marketplace. This is the only Australian event where you can exhibit your products and services to a large and high level audience of business decision makers and buyers – keen to see the latest and greatest solutions available.